Our process

Nothing hidden inside your walls.

Twelve stages from bare land to the final key — what we do, how we do it, what we check and what you receive at every step.

01
Plan stage

Site visit

We walk your land with you and listen: what you want to build, for whom, by when and on what budget.

How we do it

Founder or senior engineer on site; access road, water, power and slope noted.

What we check

Site constraints and local approvals.

You receive

A free consultation and honest first advice.

Site visit
02
Plan stage

Survey & soil

DGPS survey and contour mapping of the land; soil or rock checked where we will build.

How we do it

Survey instrument readings, levels at a fixed grid, trial pits where needed.

What we check

Levels, boundaries and bearing strata.

You receive

A contour map that is yours to keep, even for your own architect.

Survey & soil
03
Plan stage

Design

Architectural and structural drawings by our in-house team, or we build from your architect's set.

How we do it

Plans, elevations, sections, structural design and services layout.

What we check

Structural safety, Vastu if wanted, views and privacy.

You receive

A complete drawing set, finalised with you.

Design
04
Plan stage

BOQ & agreement

Every item, quantity, grade and brand written down; a stage-wise schedule agreed and signed.

How we do it

Detailed BOQ from the drawings; payment linked to stages.

What we check

Quantities and rates line by line.

You receive

A transparent BOQ and a written timeline.

BOQ & agreement
05
Build stage

Site setup

Layout marked on the ground, material yard, labour stay, water and power arranged, safety boards put up.

How we do it

Centre-line marking from drawings, reference pillars fixed.

What we check

Layout double-checked by engineer before digging.

You receive

Your first daily progress report.

Site setup
06
Build stage

Excavation & foundation

Excavation and rock cutting, PCC bed, footing steel, foundation concrete, anti-termite treatment, plinth beam.

How we do it

Our own excavators; RMC for footings; cover blocks under steel.

What we check

Depth, footing size, steel and cover before every pour.

You receive

Foundation photos and records.

Excavation & foundation
07
Build stage

RCC frame

Columns, beams and slabs: shuttering, steel, then ready-mix concrete placed by pump and compacted by vibrator.

How we do it

RMC from a batching plant; Fe550D TMT steel; curing after every pour.

What we check

Slump test on every truck, cube test at 7 and 28 days, steel check before each slab.

You receive

Photos of every slab and the test records.

RCC frame
08
Build stage

Masonry

Walls in AAC blocks or fly-ash bricks with lintels and sill bands.

How we do it

Thin-bed or cement mortar, true to line and level.

What we check

Line, level and plumb of every wall.

You receive

Weekly progress photos.

Masonry
09
Build stage

Electrical & plumbing

Concealed conduits, wiring, water supply and drainage lines laid before plaster.

How we do it

FRLS copper wiring; CPVC / uPVC pipes; layout as per drawing.

What we check

Pressure test on water lines; circuit check.

You receive

As-built services layout.

Electrical & plumbing
10
Finish stage

Plaster & waterproofing

Internal and external plaster; waterproofing of roofs, toilets, sunken areas and pools.

How we do it

Chicken mesh at RCC–masonry joints; branded waterproofing systems.

What we check

Ponding test for 48 hours before tiling.

You receive

Test photos and warranty details.

Plaster & waterproofing
11
Finish stage

Finishing

Flooring, stone cladding, paint, doors, windows, fittings and fixtures.

How we do it

Materials chosen with you from the brands in your BOQ.

What we check

Finish quality, alignment, joints and shades.

You receive

Material selection sessions with you.

Finishing
12
Finish stage

Handover

Snag list closed, site cleaned, final walk-through, documents and keys handed over.

How we do it

Joint inspection room by room.

What we check

Every item on the snag list closed.

You receive

Keys, drawings, warranties and our support after handover.

Handover
Build specification

What goes into your building.

Our standard specification. Every project gets its own BOQ with exact grades and brands, agreed before work begins.

Part of buildingMaterial & methodBrands
01FoundationRCC footings in ready-mix concrete over PCC bedAnti-termite treatment, plinth beam, compacted backfillUltraTech / ACC · Tata / JSW
02RCC frameColumns, beams and slabs in M25 RMC, pump-placedFe550D TMT steel, cover blocks, vibrator compaction, curingTata Steel / JSW / SAIL
03MasonryAAC blocks or fly-ash bricksLintels and sill bands, true to line and levelAs per BOQ
04PlasterDouble-coat external, single-coat internalChicken mesh at RCC–masonry jointsBranded cement
05WaterproofingRoofs, toilets, sunken areas and pools48-hour ponding test before tilingDr. Fixit / Fosroc / Sika
06ElectricalConcealed FRLS copper wiring, MCB / RCCB protectionModular switchesHavells / Polycab / Legrand
07PlumbingCPVC supply, uPVC / SWR drainagePressure-testedAstral / Supreme / Ashirvad
08FinishesTiles or stone, branded paint, fittings as per finish levelSelected with youKajaria · Asian Paints · Jaquar / Kohler
Quality checks

Checked before it is covered.

Once concrete is poured or plaster is done, mistakes are hidden forever. So we check first — and record it.

Slump test on every RMC truck

Workability checked on arrival; a truck out of range is sent back.

Every pour

Concrete cube test

Cubes cast from each pour and tested at 7 and 28 days.

7 & 28 days

Steel check before every slab

Bar size, spacing, laps and cover blocks checked by our engineer.

Before each pour

Curing log

Water curing after every pour, recorded in the daily report.

Daily

Pressure test on water lines

Supply lines tested for leaks before they are plastered in.

Before plaster

Ponding test

48-hour water test on roofs, toilets and sunken areas before tiling.

Before tiling
Daily progress report

Watch your building rise — from anywhere.

Every evening you get a report on WhatsApp: what was done, labour on site, material received, tests done and photos.

  • Work done today, block by block
  • Labour and machinery on site
  • Material received with brand
  • Tests and checks done
  • Photos from site
Daily Progress ReportSample
ProjectMorcha-1 Resort
Work todayBlock C · first-floor slab steel
Labour[ number ]
Material inCement · TMT steel
ChecksSteel & cover checked ✓
DPR photo
Sample layout — real reports come from site every day.
Who does it

A dedicated team on every site.

1

Site manager

Your single point of contact, responsible for the whole site.

1

Supervisor

On site every day, running work, material and safety.

5

Engineers

Planning, structure and quality checks at every stage.

500+

Skilled workforce

Masons, steel fixers, carpenters, stone and finishing crews.